COP v3.0:revision-history; 2020-september

19.11 2020 – September 

The following updates to the NZ Metal Roof and Wall Cladding Code Practice (COP) were published on 1 September 2020.

Summary of Changes in this update:

19.11A Revision Detail - 2020 - September

CategoryClause Number (at time of update)Clause (As of current publication)Details
2 - Editing and rearrangement11 IntroductionUpdate Revisions Message
2 - Editing and rearrangement2.12.1 DefinitionsRevised definitions of Gutter and Valley.
2 - Editing and rearrangement4.24.2 Metal CorrosionAdded paragraph about salt contamination.
1 - Minor Errata5.75.4.7 Gutter Capacity CalculatorClarity improvement. Inserted the Comment: "Please read with Roof Drainage Design "
1 - Minor Errata9.39.3 Penetration Durability and CompatibilityRenamed clause to be more reflective of its content.
1 - Minor Errata12.4.112.5.1 Touch-UpChanged punctuation in heading for consistency.
2 - Editing and rearrangement15.215.2 Mounting Air Conditioning, Aerials, and Solar UnitsClause has been renamed and new copy included.
2 - Editing and rearrangement1717 Testing and MRM StandardsAdded introduction.
1 - Minor Errata18.618.6 VelocitiesRemoved extra heading.
1 - Minor Errata18.718.7 Cricket Penetration PatternsFixed headings.
4 - Clause Inserted 17.4 MRM Pre-Painted Coil Standard – Performance RequirementsNew clause.
4 - Clause Inserted 17.4.1 Part1: ASNZS/2728:2013New clause.
4 - Clause Inserted 17.4.2 Part 2: Additional CriteriaNew clause.
4 - Clause Inserted 17.4.3 CommentaryNew clause.
4 - Clause Inserted 17.4.4 Appendices of AS/NZS 2728:2013 included as Normative in the MRM StandardNew clause.
4 - Clause Inserted 17.4.5 Appendices of AS/NZS2728:2013 considered Informative in the MRM Standard:New clause.
4 - Clause Inserted 17.4.6 Copyright AcknowledgementNew clause.