Code of Practice v3.0 Online
The NZ Metal Roof and Wall Cladding Code of Practice is a comprehensive design & installation guide, and a recognised related document for Acceptable Solution E2/AS1 of the NZ Building Code.
The NZ Metal Roof and Wall Cladding Code of Practice is a comprehensive design & installation guide, and a recognised related document for Acceptable Solution E2/AS1 of the NZ Building Code.
The following updates to the NZ Metal Roof and Wall Cladding Code Practice (COP), are effective 1 March 2020.
This update contains only minor revisions, mostly concerning grammar and punctuation fixes.
Editing and rearrangement for clarity
Category | Clause Number (at time of update) | Clause (As of current publication) | Details |
---|---|---|---|
2 - Editing and rearrangement | 1 | 1 Introduction | Update Revisions Message |
1 - Minor Errata | 5.2 | 5.4 Gutters | Easier to read layout options. |
1 - Minor Errata | 5.2.1 | 5.4.1 External Gutters (Spouting) | Grammar fix. |
1 - Minor Errata | 5.2.3 | 5.4.5 Internal Gutters | Grammar fix. |
2 - Editing and rearrangement | 5.2.4.2 | 5.5.2 Valley Design | Removed references to "Upstand Angle B" and replaced drawing "Common Valley Shapes" |
1 - Minor Errata | 5.2.4.6 | 5.5.6 Asymmetrical Valleys | Punctuation fix. |
1 - Minor Errata | 5.3.1 | 5.6.1 Rainwater Heads | Punctuation fix. |
1 - Minor Errata | 5.3.2 | 5.6.2 Sumps | Typo fix. |
1 - Minor Errata | 5.4 | 5.7 Outlets and Downpipes | Punctuation fix. |
1 - Minor Errata | 5.5.3 | 14.18.9 Gutter Installation | Minor Typo Fix. |
1 - Minor Errata | 5.6.2 | 5.4.2.1 Gutter Fall | Typo fix. |
1 - Minor Errata | 5.6.3.1 | 5.3.2.2 Duration | Replaced comparison chart with a simplified one. |
1 - Minor Errata | 8.9.1 | 8.9.1 Flashing Expansion | Grammar fix. |