Ground Clearance

Clearance is required between the bottom of profiled metal cladding and large flat surfaces. For timber-framed dwellings, E2/AS1 requires a clearance of 35 mm to an adjacent roof, 100 mm to paved ground, and 175 mm to unpaved ground.

A printable bulletin is available at: BGC01 Pre-Painted Metal Wall Cladding to Ground Clearance

Extract: 

"..Durability, rather than weatherproofness, motivates these clearances. The purpose of clearance
between cladding and ground surfaces is to keep the wall cladding free from build-up of vegetation or
debris, that may both be corrosive and increase time of wetness..."

The clearance requirements for unlined buildings are less than those required for lined buildings, as the absence of lining enables the inner face of the cladding to dry more rapidly, and inspection and maintenance of the framing can be practically achieved.

Importance Levels from NZS 3604:2011 (Table 1.1)

Level 1Structures presenting a low degree of hazard to life and other property
Level 2Normal structures and structures not in other importance levels
Level 3Structures that may contain people in crowds or contents of high value to the community, or may pose risks to people in crowds.
Level 4Structures with special post-disaster functions.
 

Minimum Ground Clearance for Lined Buildings

Minimum Design Ground Clearance for
Profiled Metal Cladding on Lined Buildings of Importance Level 2.
 
Ground TypeMinimum Clearance
Garage door opening25 mm
Walls under canopies35 mm
Paved100 mm
Unpaved gravel125 mm
Unpaved lawn150 mm
Unpaved pasture175 mm
 

 

Importance level 1 buildings may have a lesser clearance provided occupant maintenance prevents the build-up of debris against the cladding.

Greater clearance may be required where gardens abut a wall, where lawn grasses are not grazed or maintained, or where soil spillage from adjacent banks may occur. Future landscaping effects on ground levels must also be considered.

Clause: 
004_015_001_000_000_000_000_000_000
Clause Number: 
4.15.1
/cop/durability/clearances#ground-clearance