Apron and Parapet Capping Terminations

A junction where an apron flashing meets a ridge can be weathered by two methods.

  1. By carrying the apron over the ridge and covering the joint with the ridging as shown in Parapet/Apron Ridge Cap.
  2. By making a separate saddle flashing as shown in Separate Saddle Flashing.

1. Install soaker/underflashing to the top of the apron flashing.

2. Construct the roof and install the fascia.

3. Install the roofing underlay and cladding.

4. Install a soaker/underflashing folded over the cladding to cover a minimum of 1 rib and to the top of the apron.

 

5. Install the barge flashing.

6. Install the apron flashing, rivet and seal to the barge flashing.

7. Install a Z-flashing with a kickout to cover the top of the apron flashing.

8. Install wall cladding on cavity battens, covering the top half of the Z-flashing.

9. Apply sealant between the cladding and the flashings.

Parapet cappings should have a separate cap at the apex or be joined as shown in Parapet Ridge.

 

 

 

Clause: 
008_005_004_001_000_000_000_000_000
Clause Number: 
8.5.4.1
/cop/flashings/flashing-types#apron-and-parapet-capping-terminations
Revision Category: 
2 - Editing and rearrangement
Revision Detail: 

Title edit, layout change, and a new drawing showing details for Apron Terminations.

Draft Clause: 
007_004_004_001_000_000_000_000_000